What is the plan-to-produce process?
Plan-to-produce is the end-to-end process from production planning to the finished end product. In special machine building it covers production planning and costing, production orders for parts manufacturing and sub-assemblies, and final assembly and delivery. In the operational data it consists of customer projects, production orders, operations, confirmations and material stocks.
How do you measure schedule adherence in manufacturing at work center level?
For every operation, the planned start and planned end from the routing are compared with the actual start and actual end from the shop floor confirmations. This yields, per work center, the share of operations started late, the start delay, the duration deviation and the share of operations finished on time.
What is the difference between start delay and duration deviation?
The start delay measures how much later an operation starts than planned – the cause usually lies before the work center, for example in predecessors, material or capacity. The duration deviation measures how much longer processing takes than planned – the cause usually lies at the work center itself, for example in standard times, set-up effort or rework.
How is the waiting time between work centers calculated?
The waiting time is the time between the actual end of one operation and the actual start of the following operation at the next work center. Summed across all transitions, it shows what share of the lead time is idle time. With context such as shift calendars, batches and purchased parts, the analysis can tell what a part is waiting for.
How can tied-up capital in manufacturing be measured?
Through the stock values of the materials at the work centers: for every point in time it is known which material of which value sits where. This yields the capital tied up in work in progress per work center, production order and customer project. With an imputed interest rate, the capital cost of waiting can be quantified.
What data does Noreja need to analyse a manufacturing process?
At its core, production orders with routings and operations (work center, planned start, planned end), confirmations with actual start and actual end, and material movements or stocks with values per work center. Context such as shift calendars, breakdowns, engineering changes or quality notifications makes the analysis more explanatory but is not a prerequisite. A traditional flat event log does not have to be built first.
Why is an event knowledge graph suited to special machine building?
Because the decisive effects arise between objects: many production orders run across shared work centers, a paint batch bundles parts from different orders, and final assembly depends on several sub-assemblies at once. The event knowledge graph preserves these relationships; a flat event log per case could not explain them.
Are the figures from a real company?
No. All figures are example values from a synthetic demonstration scenario. They illustrate the analysis method and are not production figures of any customer.